Sample Deliverables
See What You Receive
Illustrative extracts from each of our four services. They show the format, the structure and the level of detail. The projects, figures and manufacturers are examples, not client data.
All samples on this page are illustrative and were prepared for this website. They do not represent any client, project or employer.
02 — Measure
BOQ Extract
An extract from a finishes package measured to NRM2. Every line carries its unit, its measurement rule and the drawing it came from.
| Ref | Description | Unit | Qty | Measurement rule | Drawing |
|---|---|---|---|---|---|
| 09-01 | Gypsum board partition, Type A: 12.5 mm board both sides on 70 mm metal studs, full height to soffit (3.20 m) | m² | 248.60 | Measured net; openings over 1.00 m² deducted | A-201, A-202 |
| 09-02 | Porcelain floor tiling FL-01, 600 × 600 mm, on 40 mm screed | m² | 312.40 | Net area; voids under 0.50 m² not deducted | A-301 |
| 09-03 | Skirting to match FL-01, 100 mm high | m | 186.20 | Measured along the wall face | A-301 |
| 09-04 | Emulsion paint PT-02, primer and two coats, to gypsum board walls | m² | 497.20 | Measured net; openings over 0.50 m² deducted | A-201 |
| 08-01 | Single-leaf timber door set D-03, 900 × 2100 mm, including frame and ironmongery set IR-02 | nr | 14 | Enumerated | A-501 |
What comes with it
- Assumption A-04: ceiling height taken as 3.20 m from section B-B, to be confirmed by the design team.
- Query Q-07: door D-03 fire rating is not shown on A-501; item priced as non-rated until confirmed.
- Every quantity is backed by a measurement sheet you receive with the BOQ.
01 — Specify
Specification Matrix
The matrix links every MasterFormat section to the drawing tags, schedule codes and BOQ items it governs, and shows what is still missing.
| Section | Title | Drawing tags | Schedule codes | BOQ items | Status |
|---|---|---|---|---|---|
| 09 21 16 | Gypsum Board Assemblies | Partition types A, B | — | 09-01 | Complete |
| 09 30 13 | Ceramic Tiling | FL-01, WC-03 | FL-01, WC-03 | 09-02, 09-03 | Grout colour to confirm |
| 09 91 23 | Interior Painting | PT-02 | PT-02 | 09-04 | Complete |
| 08 14 16 | Flush Wood Doors | D-03 | D-03 | 08-01 | Fire rating to confirm |
| 08 71 00 | Door Hardware | IR-02 | IR-02 | 08-01 | Gap: hardware set not issued |
Why it matters
- One section owns each requirement; other sections reference it.
- Gaps are listed, not left as blank clauses, so the design team knows what to resolve.
- The same section numbers carry through to the BOQ and the material schedule.
03 — Organize
Material Schedule
One code means one material everywhere: on the drawings, in the specification and in the BOQ.
| Code | Material | Location | Spec section | Manufacturer reference | Status |
|---|---|---|---|---|---|
| FL-01 | Porcelain tile 600 × 600 mm, matt, light grey | Offices, corridors | 09 30 13 | Manufacturer A or approved equal | Sample required |
| WC-03 | Ceramic wall tile 300 × 600 mm, gloss white | Toilets, wet walls to 2.40 m | 09 30 13 | Manufacturer B or approved equal | Complete |
| PT-02 | Acrylic emulsion, washable, off-white | Office walls | 09 91 23 | Manufacturer C or approved equal | Colour reference to confirm |
| CL-02 | Mineral fibre ceiling tile 600 × 600 mm | Offices | 09 51 13 | Manufacturer D or approved equal | Complete |
Notes
- Manufacturer references are potential sources only; they are not supplier approval or procurement.
- Incomplete material information is flagged in a separate gap list.
- The schedule can be delivered as Excel and, where useful, as a Power BI dashboard.
04 — Price
Bid Levelling Sheet
Three bids for the same package, brought onto one comparable basis. The lowest submitted price is not always the lowest levelled cost.
| Item (SAR) | Bid A | Bid B | Bid C |
|---|---|---|---|
| Submitted total | 1,240,000 | 1,185,000 | 1,302,000 |
| Arithmetic correction | −3,200 | — | — |
| Excluded ceiling grid, priced at pre-tender rate | — | +46,500 | — |
| Provisional sums aligned to tender | — | +20,000 | — |
| Qualification on tile grade, priced | — | — | −12,000 |
| Levelled total | 1,236,800 | 1,251,500 | 1,290,000 |
| Rank after levelling | 1 | 2 | 3 |
Reading the sheet
- Bid B was the lowest submitted price, but second after levelling.
- Every adjustment is referenced to a clarification log entry.
- Figures are illustrative. Recommendations are advisory; the award decision stays with the client.