A Bill of Quantities is priced exactly as it is written. Run these thirty checks before it goes to bidders or to your estimating team.

Most tender queries, pricing disputes and post-contract variations trace back to something that could have been caught in the BOQ: a quantity measured from a superseded drawing, a description that does not match the specification, or a material that appears on the drawings but nowhere in the bill.

This checklist groups thirty checks into six areas. Use it on your own BOQ, on one you have received for pricing, or as the brief for an independent review. It is free to print and share with your team.

Basis and scope

  • 01The measurement method is stated (POMI, NRM2, CESMM or as the contract specifies) and applied consistently.
  • 02The drawing register and the revisions used for measurement are listed.
  • 03The scope of each package is defined, including its interfaces with other packages.
  • 04Preliminaries, provisional sums and prime cost sums are identified separately.
  • 05Work by others, client-supplied items and exclusions are stated.

Structure and coding

  • 06The BOQ follows one structure throughout: MasterFormat divisions, elemental or trade.
  • 07Item references are unique and are not reused after revisions.
  • 08Each item can be traced to a specification section.
  • 09Headings and preambles follow the same structure as the specification.
  • 10Units follow the measurement method (m, m², m³, nr, item) and are used consistently.

Descriptions

  • 11Each description states material, size, thickness and finish where they affect price.
  • 12Descriptions use the same terms and codes as the drawings and schedules.
  • 13Items described “as specified” point to a specific clause, not only to a division.
  • 14Composite items state clearly what they include.
  • 15There are no placeholder descriptions such as “TBC” or “allow” without a stated basis.

Quantities

  • 16A sample re-measurement of the main items agrees within an acceptable tolerance.
  • 17Deductions for openings and voids follow the method’s rules.
  • 18Repetitive elements, such as typical floors or units, are multiplied correctly.
  • 19Quantities taken from the BIM model have been checked against the 2D drawings.
  • 20There are no zero quantities, duplicate items or unit errors, such as m² entered as m.

Coordination

  • 21Every material in the material schedule appears in the BOQ, and every BOQ material appears in the schedule.
  • 22Door, window and ironmongery counts match their schedules.
  • 23Finishes match the room finish schedule for each room type.
  • 24Work shown on the drawings but missing from the BOQ is listed.
  • 25Changes since the last drawing issue are reflected in the BOQ and recorded.

Ready to issue

  • 26Assumptions and exclusions are written into the BOQ, not kept in a separate email.
  • 27Open queries are listed with an owner and a target date.
  • 28Page totals, collections and summaries add up and carry through to the main summary.
  • 29The pricing columns are consistent and protected, so every bidder prices the same format.
  • 30The BOQ has been checked by someone other than the person who measured it.

How to use it

Review in order. The first two groups decide whether the rest are worth checking. If the measurement basis or the drawing revisions are unclear, settle them before checking quantities.

Sample, then widen. Re-measure the five or six items that carry most of the value. If they agree, widen the sample; if they do not, the problem is usually systematic and worth finding before tender.

Record what you find. A review is only useful if its findings are logged: item, issue, proposed correction and owner. That log becomes the record of what changed before issue.

If you would rather have the review done independently, QEYAS provides BOQ reviews against the drawings and specifications, with a review report and issues log.

Related service 02 Measure: BOQ review

All insights

QEYAS · qeyas.co · contact@qeyas.co

Need an independent review?

Have your BOQ checked before tender

Send us the BOQ and the drawings. We review the scope for free and propose a review with a report and issues log.

Request a BOQ review
WhatsApp